Three workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

MrRamon
MrRamon MrRamon
  • 13-04-2018
4 additional workers for 7 total workers.
if it takes 3 workers 28 hours to do work there are 84 total hours of work (3*28=84) to find how many workers it will take to get the work done in 12 hours divide 84 by 12. 84/12= 7 total workers. 7-3= 4 additional workers needed.
Answer Link
pranilraichura
pranilraichura pranilraichura
  • 08-03-2020

Answer:

4 workers

Step-by-step explanation:

Answer Link

Otras preguntas

What is one right or freedom from the First Amendment?*
Name one right only for United States citizens.
Why do some states have more Representatives than other states?
Why do some states have more Representatives than other states?
Which compound yields H + ions as the only positive ions in an aqueous solution? (1) KOH (3) CH3OH (2) NaOH (4) CH3COOH
Before he was President, Eisenhower was a general. What war was he in?
How do you multiply a decimal? For exapmple,2.4 times 3.5
Which compound yields H + ions as the only positive ions in an aqueous solution? (1) KOH (3) CH3OH (2) NaOH (4) CH3COOH
Given the balanced equation representing a reaction: 4Al(s) + 3O2(g) ==> Al2O3(s) As the aluminum loses 12 moles of electrons, the oxygen (1) gains 4 moles o
Which condensed structural formula represents an unsaturated compound? (1) CH3CHCHCH3 (3) CH3CH3 (2) CH3CH2CH3 (4) CH4