In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Each term in Pattern G is 6 times greater than the corresponding term in Pattern H. What is the rule for Pattern G? Plz help......
Senator Jon Tester of Montana was reelected in 2012. If he decides to run again when his current term expires, in what year will the election occur?
Benjamin is making bow ties . How many 1/2 yard-long bow ties can he make if he has 18 feet of fabric!
find the absolute value of each rational number |3.7|
An object will remain at rest or maintain constant, straight-line motion unless acted on by a force that is ___________________.A.inertialB.balancedC.unbalanced
Average national teachers salaries can be modeled using the equation y=9.25(1.06)^n , where y is the salary in thousands of dollars and n is the number of years
Power that comes from atoms is called ________? steam power coal power electric power nuclear power
Let “x” be the number of apples in a barrel. Which of the following is the expression that represents one less than twice the number of apples in the barrel?
which best describes the relationship of the embryo and the fetus.
Where would you look for glacial grooves in the 300 million year old rock of Antartica?