15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

In which of these situations would the answer to the question be 0? A) The low temperature one day was -10°F. The high temperature that day was 10 F. What is th
You are infected with a pathogen; it is your first exposure to this pathogen. The first antibody types that will eventually appear in your blood to help fight t
I NEED HELP RIGHT NOWW! What issues are on the United Nations agenda for sustainable development for 2015?
A restaurant keeps eggs in a rack that has 5 layers each layer has 5 row with 5 eggs in each row
Hey brainly community.. Ive got a question. If you have ever had a missing cat.. what helped you find her/him. My cat gets scared very easy and has been missing
Provide an example of how creating a pattern, then breaking it, could enhance the visual design of a hypothetical game.
How did mendel prove the law of segregation.
PLS HELP WILL MARK YOU BRAINLIEST!
Gemma is solving a division problem. After writing the problem down, she moves the decimal point directly up to the quotient. Which of these is true of Gemma’s
6.4 + 3.2? I need it in simplist form